Butyl Drainage Plane Flashing
Self-Adhering Through-Wall Flashing
- Install membrane on a clean, dry, and smooth surface.
- Install where indicated, specifed, or required following the manufacturer’s written instructions and as follows.
- Overlap end joints a minimum of four inches, and seal the leading edge with York's Universeal US-100 sealant at lap joint locations.
- Seal all terminations, detailing, edges, and protrusions with York's Universeal US-100.
- Membrane must be held back 1" from the face of the veneer and sealed with York's US-100 sealant.
- Install the membrane using a hard roller and roll the membrane with constant, firm pressure to ensure uniform contact with the substrate.
- When installing the membrane at a 90° or greater angle, prebend the membrane and roll the crease before removing the release liner and installation.
- Confirm compatibility when installing the membrane over an air barrier, sealants, or below grade waterproofng and those items must be fully cured.